Hanoi capital tests metro trains on overground route
The Hanoi capital on July 1 carried out a test run of its trains on the overground track under the Nhon-Hanoi Railway Station Metro project before it is officially put into operation later this year.
MPS to pilot the building of “Exemplary ward police post” in metropolises
Two more Japanese-made metro trains arrive in Khanh Hoi port
HCM City set to become smart metropolis
The six trains are put into operation on a trial basis on the line’s 8.5km long elevated section running from the Nhon Depot area in Nam Tu Liem district to Station S8 in Cau Giay district.
According to Le Trung Hieu, deputy head of the Hanoi Metropolitan Railway Management Board (MRB), the project has so far received six out of a total of 10 trains manufactured in France.
The trains are conducted by experienced drivers of the French manufacturer Alstom Company.
Approximately 73% of the project’s workload has been completed so far.
The 10 trains which will run as part of the Nhon-Hanoi Railway Station Metro project have been designed and manufactured by Alstom. The first train initially arrived on October 18, 2020.
The trains initially depart at 10:30 a.m. on July 1 from the Nhon Depot area, running through Nhon-Ho Tung Mau-Cau Giay streets.
The trains prepare to reach their destination at Station S8 in Cau Giay district.
After arriving at Station S8, the trains return to their Nhon Depot.
The trains pass through Mai Dich Station.
The Nhon-Hanoi Railway Station metro route runs for a total of 12.5 kilometres, including 8.5 kilometres overground and four kilometres underground. The overground section is due to be put into operation later this year, and the underground section by late 2022
The six trains are put into operation on a trial basis on the line’s 8.5km long elevated section running from the Nhon Depot area in Nam Tu Liem district to Station S8 in Cau Giay district.
According to Le Trung Hieu, deputy head of the Hanoi Metropolitan Railway Management Board (MRB), the project has so far received six out of a total of 10 trains manufactured in France.
The trains are conducted by experienced drivers of the French manufacturer Alstom Company.
Approximately 73% of the project’s workload has been completed so far.
The 10 trains which will run as part of the Nhon-Hanoi Railway Station Metro project have been designed and manufactured by Alstom. The first train initially arrived on October 18, 2020.
The trains initially depart at 10:30 a.m. on July 1 from the Nhon Depot area, running through Nhon-Ho Tung Mau-Cau Giay streets.
The trains prepare to reach their destination at Station S8 in Cau Giay district.
After arriving at Station S8, the trains return to their Nhon Depot.
The trains pass through Mai Dich Station.
The Nhon-Hanoi Railway Station metro route runs for a total of 12.5 kilometres, including 8.5 kilometres overground and four kilometres underground. The overground section is due to be put into operation later this year, and the underground section by late 2022.
The six trains are put into operation on a trial basis on the line’s 8.5km long elevated section running from the Nhon Depot area in Nam Tu Liem district to Station S8 in Cau Giay district.
According to Le Trung Hieu, deputy head of the Hanoi Metropolitan Railway Management Board (MRB), the project has so far received six out of a total of 10 trains manufactured in France.
The trains are conducted by experienced drivers of the French manufacturer Alstom Company.
Approximately 73% of the project’s workload has been completed so far.
The 10 trains which will run as part of the Nhon-Hanoi Railway Station Metro project have been designed and manufactured by Alstom. The first train initially arrived on October 18, 2020.
The trains initially depart at 10:30 a.m. on July 1 from the Nhon Depot area, running through Nhon-Ho Tung Mau-Cau Giay streets.
The trains prepare to reach their destination at Station S8 in Cau Giay district.
After arriving at Station S8, the trains return to their Nhon Depot.
The trains pass through Mai Dich Station.
The Nhon-Hanoi Railway Station metro route runs for a total of 12.5 kilometres, including 8.5 kilometres overground and four kilometres underground. The overground section is due to be put into operation later this year, and the underground section by late 2022.
Under the plan, all central and local media outlets are required to launch columns on the campaign, maintain regular coverage, and produce at least five to seven in-depth reports each month in key search areas. Media agencies will also be encouraged to gather and verify valuable information and develop high-quality products in both Vietnamese and foreign languages, including feature articles, documentaries, reports and short videos.
Ambassador Pham Quang Hieu expressed confidence that the establishment will serve as a strong spiritual anchor for Vietnamese people living in Japan while contributing to friendship and cultural exchanges between the two countries.
Cyberspace now runs through children’s learning, entertainment, and daily lives, but warned it is laced with dangerous content, online insults, threats, and seemingly harmless clicks that can trigger fraud, data breaches, and risks children who are not yet equipped to handle.
Cambodia’s General Department of Immigration under the Ministry of Interior deported the group for violations of regulations related to immigration, labour and residency.
A scholar has stressed the need for Vietnam to make use of cooperation opportunities arising from the RoK’s foreign policy, particularly in semiconductor technology, artificial intelligence (AI), supply chains, digital transformation, and green energy, as well as chances in multilateral diplomacy.
Protecting children in the digital environment is becoming an increasingly urgent issue as children gain access to the internet earlier and face growing online risks.
The citizens, whose registered living places, are mainly in northern, central, Central Highlands, and southwestern localities, had travelled to Cambodia through different border gates at various times.
VOV.VN - Vietnam’s competent agencies have dismantled a self-proclaimed organisation known as “Bahnar Dega Kon Kong” in the Central Highlands, describing it as a variant of the outlawed “Dega Protestantism” movement allegedly directed by overseas FULRO-linked extremists.
Police in Ho Chi Minh City have filed charges against 35 people with illegally storing and trading toxic substances in connection with a large-scale cross-border cyanide smuggling ring, investigators said on May 23.
Pham Van Hat is best known as the creator of the made-in-Vietnam “Seed Sowing Robot,” now exported to 15 countries, alongside dozens of practical inventions that have eased labour for thousands of farmers.
Films, music, television programmes, e-books, video games, journalistic works, images and creative data can now be copied, edited and redistributed within minutes. While copyright violations were once linked mainly to pirated discs or counterfeit books, infringements have shifted online with faster speed, wider scale and greater anonymity.
Consul General Nguyen Viet Kien stressed President Ho Chi Minh’s reputation and career transcended Vietnam’s borders to inspire liberation movements worldwide, and that his ideas on the right to self-determination, peace, and friendship among nations remain deeply relevant today.
Party General Secretary and State President To Lam stressed that citizens should have access to stable, safe and affordable housing suited to eligible beneficiaries, with rental housing becoming a long-term pillar.
Sailing Ship 286 – Le Quy Don of the Vietnam People’s Navy (VPN) departed on May 16 for a diplomatic and training voyage to Thailand and Cambodia, combining naval exchanges with long-distance maritime training for cadets.
A key target under the new plan is the establishment of five digital technology incubators, or Deeptech Hubs, at universities and research institutes with strong potential. The education ministry also plans to launch a training programme for 1,000 outstanding technology entrepreneurs and develop criteria for selecting and supporting startup ecosystems within educational institutions.
During the second phase of the 25th campaign, nearly two months of operations under challenging terrain and weather conditions, as well as the dangers posed by unexploded ordnance, enabled search teams to recover 158 sets of remains, bringing the total number recovered during the campaign to 322.
To accelerate the implementation of the the Ethnic Affairs Strategy by 2030, with a vision toward 2045, the Prime Minister requested ministries, agencies and local authorities to continue thoroughly carrying out the Party and State’s policies on ethnic affairs, enhancing the effectiveness of State management and strengthening oversight of policy implementation.
Vietnamese authorities also provided the Chinese side with photographs and video footage recording the rescue operation and repairs to the vessels, demonstrating transparency and Vietnam’s full efforts in maritime search and rescue.
The team examined the APEC 2027 Convention Centre, where main conference activities are scheduled; Sun Serenia Hospital, designated to provide healthcare and emergency medical services for delegates; provincial road DT.975, which connects Phu Quoc International Airport to the convention centre; and the area surrounding Phu Quoc International Airport.